Cost overruns could mean fewer infrastructure projects

Advertisement

Want the latest procurement and supply chain news delivered straight to your inbox? Sign up for the Supply Management Daily

16 January 2013 | Adam Leach

The government may not be able to proceed with all of its planned infrastructure projects or may be forced to place the burden on taxpayers, unless it keeps the costs under tight control.

A report by the National Audit Office (NAO) published today, Planning for economic infrastructure, identified five key factors which it believes could threaten the value-for-money case on the government’s infrastructure plans.

These were: inaccurate identification of the need for infrastructure; policy uncertainty; failure to assess the cumulative impact on consumers of funding infrastructure through user charges; taxpayer exposure to losses; and delivery costs higher than they should be.

The government has earmarked £310 billion to be spent on infrastructure, with £257 billion to be spent by 2020, but the NAO said if, as is historically the case, the costs continued to be higher than in other European countries, the number of projects might have to be trimmed.

“UK infrastructure costs have historically been higher than overseas. This could result in high costs for taxpayers and consumers and fewer projects going ahead than planned,” the study said.

It also identified “policy uncertainty” as a major risk, arguing unless there is clear and consistent policy, contractors, investors and sponsors might look elsewhere.

The NAO recommended when embarking on infrastructure projects, government departments should subject their forecasts of demand for users of the infrastaucture to rigorous testing. It also said the Treasury, departments and regulators should work with the private sector and project sponsors to develop and use ‘should cost’ models – where costs are estimated through discussions with partners and potential collaborators - to test or challenge forecasted project costs.

Amyas Morse, head of the NAO, said in a statement: “Economic infrastructure keeps the country running. Demand for infrastructure is set to increase, fuelled by population growth, technological progress, climate change and congestion. But there is a lot at stake in taking forward the national infrastructure plan in an environment of straitened resources, with real risks to value for money and uncertainty about the sustainability of piling costs on to consumers.”

Configure your Portal

  • Main (left)
Configuration
WHITEPAPER:
"Putting Down a Marker"
PMMS "Putting down a marker" whitepaper cover
REPORT: "Guide to Salaries 2013"
Michael Page salary survey 2013 cover
INFOGRAPHIC
"Business Traveller Report 2012"
Egencia-Business Traveller Report 2012 - Infographic - banner
CPO Agenda logo
Live Webinar series. Click here for sponsorship opportunities.
Interserve
"How to add value to FM procurement"
Click here to watch the webinar

The winners of the CIPS Supply Management Awards 2012 have been announced. Click here to find out who was victorious and click here to watch video interviews with the winners.

Buyography blog logo
  • Finding the right funder
    Procurement principles can also be applied by public sector organisations looking for the right investment partner, says Pete Gladwell. 22 May 2013
PMI reports logo

Check out the latest commodity prices.

View latest prices

  • Main (right)
Configuration
REPORT:
"A Guide to Contract Management"
Bravo - A guide to contract management image
WHITE PAPER:
"Ten Strategies for Best-in-Class Public Sector Procurement"
top 10 strategies
WHITE PAPER:
"Value Creation: The EIPM Surfboard Shop":

EIPM - Surfboard Shop whitepaper cover
WHITE PAPER
"Global Travel Forecast: A Guide for Pricing and Negotiation in 2013"
Egencia button
WHITE PAPER:
"Forrester Research - Economic Benefits of Supplier Information Management Solution 2012"
Forrester Report
Q & A icon

Need advice on a procurement & supply chain or work-related matter?

Click here to get free expert advice.

Comments
Please enter your comments below
Fill out the all the boxes and click the 'Submit comments' button to make a comment on this page
*Comments are added to the bottom of the page. They are moderated and will not be published until approved by the Supply Management team. They may be edited. Please note unless marked “confidential” your feedback may be published on our letters page