‘Arbitrary’ equipment delays inflate defence costs

Advertisement

23 March 2010 | Jake Kanter

Bloated costs and delayed procurement projects at the UK Ministry of Defence (MoD) have come under scrutiny again today.

A report by the Public Accounts Committee (PAC) said intentional and “arbitrary” decisions to delay major equipment programmes had increased costs and resulted in “poor value for money”.

It follows a report by the National Audit Office last year, which criticised the MoD’s “save now, pay later” approach. The review showed that 15 major defence projects were running 24 months late and 8 per cent over expected cost.

The PAC accused the MoD of being “overly optimistic” about the defence budget deficit, which the MPs believe could be as high as £36 billion. A similar review by the Commons Defence Committee earlier this month slammed the department for being “disingenuous” about its equipment budget shortfall.

“That the MoD has got itself into such a mess is an indictment of its current governance and budgetary arrangements,” said PAC chairman Edward Leigh.

The MoD should develop common measures for the cost and risks of equipment programmes, including assessments of commercial skills and the maturity of new technology, the PAC report said.

It added: “In future the department must ensure that decisions to accelerate or slow down projects, or change the numbers or capabilities of equipment, are supported by quantified operational and financial analyses to enable the full costs and benefits to be identified and compared on a like-for-like basis.”

Shadow defence secretary Liam Fox said the report had a “weary familiarity” and called for a “root and branch” procurement overhaul.

Quentin Davies, minister for Defence Equipment and Support, said: “The MoD currently manages some 2,000 projects and over the past two years, 90 per cent have been delivered to cost and 80 per cent have been delivered to time.

“The government is taking the tough decisions necessary to ensure that a strong equipment programme stays within the parameters of a rising MoD budget.”

The review follows the MoD’s decision yesterday to award a contract for light tanks to US defence supplier General Dynamics. The company beat UK competitor BAE Systems to the contract.

Configure your Portal

  • Main (left)
Configuration
CIPS SM Awards Logo 2012

The deadline to enter this year's CIPS Supply Management Awards has now passed. The shortlist of nominations will be announced on 21 June.

Click here for details of how to book your table.
WHITE PAPER


"Shape up with NRI - prepare and plan your negotiations better"

Reading Lines
Buyography blog logo
PMI reports logo

Check out the latest commodity prices.

View latest prices

  • Main (right)
Configuration
WHITE PAPER:
"Top Ten Technologies - Industry Report"
Top 10 Tech Supply Management_UK
WHITE PAPER:
"Driving Lasting Savings with Spend Compliance"
lasting savings
SAP

FREE WEBINAR


"Practical steps to strategic sourcing"

Click here to view the webinar

Q & A icon

Need advice on a procurement & supply chain or work-related matter?

Click here to get free expert advice.

Comments
Please enter your comments below
Fill out the all the boxes and click the 'Submit comments' button to make a comment on this page
*Comments are added to the bottom of the page. They are moderated and will not be published until approved by the Supply Management team. They may be edited. Please note unless marked “confidential” your feedback may be published on our letters page