Pressetext v Austria

Advertisement

24 September 2009 | David Gollancz & Nicola Sewell

What changes are necessary in a contract for it to be considered a new agreement?


THE CASE

In 1994 the Austrian Republic entered a contract for an indefinite period with APA, a news service provider, waiving its right to terminate until 31 December 1999. The contract allowed the authorities to access information and press releases and use the original text service (OTS). In September 2000, APA established a wholly-owned subsidiary, APA-OTS, and transferred its OTS service to it.

The parties entered a supplemental agreement to the contract in 2001 when Austria joined the euro, rounding off some prices, substituting the price index, entering a second supplemental agreement in 2005 waiving termination rights until December 2008, and reducing the price of online enquiries.

Rival agency Pressetext challenged on the basis that the original agreement was severed following APA's restructuring in 2000, and the supplemental agreements were unlawful. The European Court of Justice (ECJ) stated amendments to a public contract only constitute a new award when they are materially different from the original contract and demonstrate the intention of the parties to renegotiate the essential terms of that contract.

None of the changes were materially different.

APA-OTS had separate legal personality to APA but it was a wholly-owned subsidiary and APA continued to assume responsibility under the contract, meaning it was an internal reorganisation. The adjustment to the euro prices was minimal and objectively justified. The contract provided for updating the price index. It was for an indefinite period and there was no suggestion the authority would have terminated it, so the increased waiver period did not distort competition. The price reduction could be considered to come under the terms of the contract and was to the detriment of APA, so did not shift the economic balance in its favour.

An amendment may be regarded as material when (a) it introduces conditions which, had they been part of the initial award procedure, would have allowed for the admission of tenderers other than those initially admitted, or for the acceptance of a tender other than the one initially accepted; (b) it extends the contract's scope to encompass services not initially covered. Or (c) it changes the economic balance in favour of the contractor in a manner not provided for in the initial contract.


WHAT THIS MEANS

This case sets out useful guidance on what constitutes a material change.

Small price amendments, especially those which work against the contractor's interests, will not constitute such a change. Where the change falls within one of the three situations set out by the ECJ, consideration must be given to whether it demonstrates an intention to renegotiate the essential terms of the contract. If so, a new award must be made.

It would be wise to include provisions for foreseeable change in contracts, because where the contract allows for a particular change the issue will not arise.

The ECJ noted that substitution of a contractual partner would amount to a material change unless it was provided for in the contract, such as through provision for sub-contracting


* By David Gollancz, partner, and Nicola Sewell, trainee solicitor, Field Fisher Waterhouse

Configure your Portal

  • Main (left)
Configuration
CIPS SM Awards Logo 2012

The deadline to enter this year's CIPS Supply Management Awards has now passed. The shortlist of nominations will be announced on 21 June.

Click here for details of how to book your table.
WHITE PAPER


"Shape up with NRI - prepare and plan your negotiations better"

Reading Lines
Buyography blog logo
PMI reports logo

Check out the latest commodity prices.

View latest prices

  • Main (right)
Configuration
WHITE PAPER:
"Top Ten Technologies - Industry Report"
Top 10 Tech Supply Management_UK
WHITE PAPER:
"Driving Lasting Savings with Spend Compliance"
lasting savings
SAP

FREE WEBINAR


"Practical steps to strategic sourcing"

Click here to view the webinar

Q & A icon

Need advice on a procurement & supply chain or work-related matter?

Click here to get free expert advice.

Comments
Please enter your comments below
Fill out the all the boxes and click the 'Submit comments' button to make a comment on this page
*Comments are added to the bottom of the page. They are moderated and will not be published until approved by the Supply Management team. They may be edited. Please note unless marked “confidential” your feedback may be published on our letters page